McFour were employed by BAM to complete the drainage works required in a maintainers yard adjacent to the Huddersfield Station. This involved drainage up to 3.5m in depth which included a Flow Control chamber and Bypass Separator.
The new drainage system needed to be connected to an existing brick culvert sewer system. The design for the new chamber to be constructed on top of this culvert would have meant its complete removal and replacement with a concrete channel. McFour suggested an alternative solution that retained the base of the brick culvert removing the requirement for over pumping and enabling the brick channel to remain